02-06-2024, 02:49 PM
The video https://www.youtube.com/watch?v=7VkhaBmQ...imodalNews gives details about land acquisition status.
It goes through 3 districts: Angul, Deogarh, Sundargarh
Angul district: 222.55 hector private land required (all is acquired); 82.08 hector govt. is required (77.581 hector has been acquired) - rest to be acquired by February 2024 end.
Deogarh district: 77.74 hector private land required - 23.07 hector is acquired rest to be acquired by February 2024 end.
32.96 hector govt. land required - 9.817 hector is alienated, rest to be acquired by February 2024 end.
Sundargarh district: 100.37 hector private land required - 70.905 hector is acquired and rest to be acquired by February 2024 end.
55.89 hector govt. land - 27.37 hector is alienated and rest to be acquired by February 2024 end.
Tender up to Pallahara; The reaming tender from Pallahara to Bimlagarh will be done as a single unit.
It goes through 3 districts: Angul, Deogarh, Sundargarh
Angul district: 222.55 hector private land required (all is acquired); 82.08 hector govt. is required (77.581 hector has been acquired) - rest to be acquired by February 2024 end.
Deogarh district: 77.74 hector private land required - 23.07 hector is acquired rest to be acquired by February 2024 end.
32.96 hector govt. land required - 9.817 hector is alienated, rest to be acquired by February 2024 end.
Sundargarh district: 100.37 hector private land required - 70.905 hector is acquired and rest to be acquired by February 2024 end.
55.89 hector govt. land - 27.37 hector is alienated and rest to be acquired by February 2024 end.
Tender up to Pallahara; The reaming tender from Pallahara to Bimlagarh will be done as a single unit.