KB Khurda-Balangir line: fast progressing - to be completed by 2027
#17
The article https://pragativadi.com/khurda-road-bala...e-by-2026/ dated March 10, 2024 has a lot of details about the current status of this line. It also mentions a bit of the history of this line. Following are some excerpts:


Quote:Khurda Road—Balangir Rail Line Boasts 7 Tunnels; Project To Complete By 2026

Rail line between Sonepur to Adhenigarh to be completed by May 2024
By Yajati Keshari Rout Last updated Mar 10, 2024

Bhubaneswar: Indian Railways’ much-awaited Khurda Road–Balangir Rail Line project will build a new rail link between western and coastal Odisha, connecting six districts in its route – Balangir, Sonepur, Phulbani, Boudh, Nayagarh, and Khurda.

The total budget of the project is Rs 3799 crore and is expected to be completed by 2026.

...

It has also been targeted to complete the rest of the stretch, i.e., from Daspalla to Purunakatak, a stretch of 75 km is expected to be completed by Dec’2026.

Accordingly, the Railways have planned 7 tunnels in the route. In Boudh District, four tunnels are being constructed while Tunnel 5 has been completed and finishing work will be done. Also, construction of Tunnels 4, 6 & 7 is underway.

... The combined length of tunnels T4, T5, T6, and T7 is a staggering 7.492 kilometres, including an escape tunnel spanning 700 meters.

Here’s a closer look at each tunnel:-.

Tunnel T4: This engineering marvel stretches from Km 156+231.5 to Km 160.415, boasting an extraordinary length of 4185 meters, there’s also a 700-meter escape tunnel ensuring safety.

Tunnel T5: Tunnel T5 covers a distance from Km 164+464 to Km 164+780.68, spanning 317 meters.

Tunnel T6: With a length of 315 meters, Tunnel T6 extends from Km 165+000.6 to Km 165+279.8.

Tunnel T7: With a length of 1975 meters, Tunnel T7 extends from Km 168+528.1 to Km 170+501.7.
Rail Bridge Over Tel River

The most important aspect of the project is the Rail Bridge on River Tel connecting the Sonepur and Boudh Districts.

...

This river connects with Mahanadi after 1&1/2 km and when the Mahanadi water level grows, the water at Tel Bridge flows reverse.

Viaduct to protect forest, wildlife movement

Railways are constructing a viaduct in a forest area between Banigochha and Adhenigarh.

...

With the recent planned opening of the Ex-Sonepur-Jharmunda section, (Length Km: 28.765) the section between Khurda(455.340KmF/HWH)-Balangir(300.838Krn) will be operational at 182.555 Km out of 301 Km of Khurda Road-Balangir Rail Line Project. (From Balangir-End).

The sanctioned cost of all the parts and detailed estimate of the entire project stands at Rs 3799 Cr. Phase-I i.e. Khurda Road-Begunia section (32.000Km) is the starting portion of the Khurda Road-Balangir B.G. Rail Line Project (Length 301Km.) taking off from Khurda Road Station (Km:455.340 F/HWH) of Howrah-Madras Line, Khurda Road Division, E.Co.Railway, Khurda Dist. Of Odisha State and the same was commissioned on 16.07.2015 for passenger traffic.

The next block section Begunia -Rajsunakhala was commissioned on 20.03.2017. The block section Rajsunakhala – Bolagarh Road was commissioned on 19.06.2017. The block sections between Nayagarhtown – MahipurdiMahipur- Nuagaon were commissioned on 26.12.2019 and 30.06.2022. The block section between Bichhupali-Balangir was commissioned on 15.01.2019, Jhartarbha-Bichhupali section was commissioned on 10.11.2022. Khambeswarpalli-Jhartarbha was commissioned on 12.07.2023. And, Sonepur-Khambeswarpalli was commissioned on 29.12.2023.
Reply


Messages In This Thread
RE: Khurda-Balangir line - by Chitta - 07-01-2022, 06:04 PM
RE: Khurda-Balangir line - by Chitta - 07-17-2022, 03:59 PM
RE: Khurda-Balangir line - by Chitta - 09-28-2022, 06:54 PM
RE: Khurda-Balangir line - by Chitta - 01-02-2023, 04:55 PM
RE: Khurda-Balangir line - by Chitta - 02-13-2023, 12:15 AM
RE: Khurda-Balangir line - by Chitta - 06-13-2023, 07:21 PM
RE: Khurda-Balangir line - by Chitta - 07-27-2023, 06:00 AM
RE: Khurda-Balangir line - by Chitta - 07-29-2023, 05:31 PM
RE: Khurda-Balangir line - by Chitta - 07-29-2023, 05:54 PM
RE: Khurda-Balangir line - by Chitta - 12-21-2023, 01:44 AM
RE: Khurda-Balangir line - by Chitta - 01-03-2024, 05:15 PM
RE: Khurda-Balangir line - by Chitta - 02-04-2024, 03:00 AM
RE: Khurda-Balangir line - by Chitta - 02-07-2024, 07:54 PM
RE: Khurda-Balangir line - by Chitta - 02-12-2024, 06:18 PM
RE: Khurda-Balangir line - by Chitta - 04-15-2024, 01:12 AM
RE: Khurda-Balangir line: fast progressing - to be completed by 2027 - by Chitta - 07-20-2024, 05:24 PM

Forum Jump:


Users browsing this thread: 2 Guest(s)