Following are some news snippets:
December 23 2022: https://www.financialexpress.com/infrast...e/2924796/
February 1, 2023: https://www.newindianexpress.com/states/...43340.html
Following are from Twitter: https://twitter.com/AIBSNews24/status/16...0779757570
![[Image: FpFosytagAAh-Of?format=jpg&name=medium]](https://pbs.twimg.com/media/FpFosytagAAh-Of?format=jpg&name=medium)
![[Image: FpFota4aQAcNVBf?format=jpg&name=medium]](https://pbs.twimg.com/media/FpFota4aQAcNVBf?format=jpg&name=medium)
![[Image: FpFot-xaEAAaDe2?format=jpg&name=medium]](https://pbs.twimg.com/media/FpFot-xaEAAaDe2?format=jpg&name=medium)
December 23 2022: https://www.financialexpress.com/infrast...e/2924796/
Quote:Angul-Sukinda New Line Project near completion; 90 per cent of work done.
Progress report and completed works of Angul-Sukinda New Line Project:
• Physical progress – 90%
• Major bridges – 21/23
• ROB/RUB – 58/58
• Track Linking – 85.4 km
• Minor Bridges – 230/230
February 1, 2023: https://www.newindianexpress.com/states/...43340.html
Quote:Angul-Sukinda new line ready for regular train ops
Official sources said the 94 km new rail line built at a cost of around Rs 2,800 crore will be commissioned by February 15 after the senior grade administrative officers’ committee submits its technical report.
Trial run of a goods train on the newly constructed Angul-Sukinda line that passes through Angul, Dhenkanal and Jajpur was successfully carried out on Monday.
Following are from Twitter: https://twitter.com/AIBSNews24/status/16...0779757570