Following are some numbers that are mentioned in https://tathya.in/1640-cr-sanctioned-for-scb/
- Rs 1640.87 crore: Amount sanctioned by state government so far
- 5000 beds: Total beds after the redevelopment
- Rs 4474 crore: Projects undertaken in the first phase to be completed by 2024
- Rs 2636.20 crore : L&T to redevelop the clinical part using that amount. 4 clinical blocks (B+G+9) & 2 utility blocks. 4240 The four clinical blocks are—general medicine, specialised medicine, specialised surgery and general surgery & trauma.
- Rs 888.50: NCC limited to redevelop the residential part using that amount
- Rs 4474.49 crore: Amount for which administrative approval has been accorded
- Rs 706.34 crore: Expenditure made till 21st Feb 2023.
- 4240 : Total number of IPD beds after completion (current number is 2182 beds)
- 13 towers comprising 672 residential units and 2278 rooms in 3 residential pockets namely Kathajodi Residency, Birupa Residency and Mahanadi Residency.
- G+2 SCB DAV Public School & Allied Infrastructure
- Rs. 130.18 crores - Other works such as development of playground, parking, Dharamsala, BOSE Guest House, SEED Corporation Building, Lift Irrigation Quarters, SRC Office Building, Leather Corporation Building, Textile office, 3 Foot Over Bridges, Red Cross Blood Bank, STP, Aahar Kendra