Ring Road - Progress
#3
Following is from https://themetrorailguy.com/nhai-odisha-...us-update/ 

Odisha Capital Region Ring Road – Information & Status

110.87 km Odisha Capital Region Ring Road (CRRR) project by NHAI is an approved 6 lane access-controlled highway around Bhubaneswar and Cuttack, Odisha.
This 6 lane expressway will connect Rameswar in Khurda district with Tangi, with an aim to allow vehicles on national highway NH-16 to bypass Khordha town, Bhubaneswar, Athagarh town, Cuttack & Choudwar town.
CRRR’s alignment was finalized in April 2021. Land acquisition started in June 2022.. The project’s Detailed Project Report (DPR) is unavailable. Its foundation stone has not yet been laid.
  • Total Estimated Cost: Rs. 5,744 crore

  • Project’s Total Length: 110.87 km

  • Lanes: 6

  • Status: Land Acquisition & Bidding Underway

  • Deadline: N/A

  • Owner: National Highways Authority of India (NHAI)

  • Project Model: Engineering, Procurement, and Construction (EPC)

Tenders & Contractors
NHAI started inviting tenders (bids) for CRRR’s construction works in October 2022 with a 2 year construction deadline.

Package & Chainage: Status



Package 1: Design Km. 0.000 to Km. 40.700
Bidding Underway

Package 2: Design CH.40.700 to 70.995 (village Bilipada to Gobindpur)
Bidding Underway

Package 3: Gobindpur near Kuspangi (NH-42) to Tangi near Bandalo Toll Palza (NH-16) Design Km.70.540 to Km. 110.870
Bidding Underway
Reply


Messages In This Thread
Ring Road - Progress - by Chitta - 02-11-2021, 01:53 AM
RE: Ring Road - Progress - by Chitta - 04-22-2021, 09:00 PM
RE: Ring Road - Progress - by Chitta - 04-23-2023, 06:47 PM
RE: Ring Road - Progress - by Chitta - 07-02-2023, 04:23 AM
RE: Ring Road - Progress - by Chitta - 07-25-2024, 03:20 AM
RE: Ring Road - Progress - by Chitta - 07-25-2024, 03:26 AM