30th Dece 2024:
As per https://themetrorailguy.com/2024/12/30/i...tion-work/
As per https://themetrorailguy.com/2024/12/30/i...tion-work/
Quote:IL&FS Engineering and Construction Company Ltd. has announced Ceigall India has awarded it a portion of Bhubaneswar Metro’s Phase 1 project’s civil construction work between Trisulia Square – Biju Patnaik Airport.
The scope of this Rs. 302.82 crore subcontract includes part design and construction of 10.97 km Package BBC-05’s viaduct at the northern-end of 26 km Line-1. This is the longest of all 3 main-line civil packages and links KIIT Square and Trisulia Square via 6 elevated stations at Nandan Vihar, Raghunathpur, Nandankanan Zoological Park, Barang Station, Phulapokhari, Trisulia Square.
Its scope also includes a ramp leading to Phulapokhari Depot & Workshop which will be built by M I A Construction under Package BBC-02 on a 16 hectare parcel.