Ring Road - Progress
#1
[Image: 2228650.jpg]
Reply
#2
Following is from https://pragativadi.com/odisha-cm-approv...ring-road/ .

Quote:Chief Minister Naveen Patnaik has approved the alignment of the Capital Region Ring Road (CRRR).

Bypassing Khordha Town, Bhubaneswar, Athagarh, Cuttack, and Choudwar, the 111.2 km CRRR will be developed as a 6-lane carriageway. The project will be completed in 30 months.

According to the Works department, Rs 600 crore from state budget towards cost of land acquisition will be provided to NHAI for taking up this project.


[Image: Ezk9iSvVcAEVomb.jpg]


Attached Files Thumbnail(s)
   
Reply
#3
Following is from https://themetrorailguy.com/nhai-odisha-...us-update/ 

Odisha Capital Region Ring Road – Information & Status

110.87 km Odisha Capital Region Ring Road (CRRR) project by NHAI is an approved 6 lane access-controlled highway around Bhubaneswar and Cuttack, Odisha.
This 6 lane expressway will connect Rameswar in Khurda district with Tangi, with an aim to allow vehicles on national highway NH-16 to bypass Khordha town, Bhubaneswar, Athagarh town, Cuttack & Choudwar town.
CRRR’s alignment was finalized in April 2021. Land acquisition started in June 2022.. The project’s Detailed Project Report (DPR) is unavailable. Its foundation stone has not yet been laid.
  • Total Estimated Cost: Rs. 5,744 crore

  • Project’s Total Length: 110.87 km

  • Lanes: 6

  • Status: Land Acquisition & Bidding Underway

  • Deadline: N/A

  • Owner: National Highways Authority of India (NHAI)

  • Project Model: Engineering, Procurement, and Construction (EPC)

Tenders & Contractors
NHAI started inviting tenders (bids) for CRRR’s construction works in October 2022 with a 2 year construction deadline.

Package & Chainage: Status



Package 1: Design Km. 0.000 to Km. 40.700
Bidding Underway

Package 2: Design CH.40.700 to 70.995 (village Bilipada to Gobindpur)
Bidding Underway

Package 3: Gobindpur near Kuspangi (NH-42) to Tangi near Bandalo Toll Palza (NH-16) Design Km.70.540 to Km. 110.870
Bidding Underway
Reply
#4
As per https://sambadepaper.com/imageview_61290..._1_sf.html there has been slight change to not disrupt elephants and allow them free movement near Kapilas. Thus a 6.78 km flyover near Kapilas would be incorporated in the plan with an additional cost of 500 crores. The central government has approved this extra expenditure. The project is expected to get done in 30 months.
Reply
#5
Following map from https://www.facebook.com/photo?fbid=7982...7315572953 shows where the ring road meets close in on the coastal highway.

[Image: attachment.php?aid=648]
Reply
#6
Following is from Sambada.

[Image: attachment.php?aid=649]

[Image: attachment.php?aid=650]


Attached Files Thumbnail(s)
       
Reply
#7
Following is from https://www.facebook.com/permalink.php?s...8800645211

[Image: attachment.php?aid=747]

[Image: attachment.php?aid=748]


Attached Files Thumbnail(s)
       
Reply
#8
Is this - from https://x.com/BDA_BBSR/status/1565221760...61/photo/1 (posted in 2022) - an inner ring road in making?

[Image: attachment.php?aid=749]


Attached Files Thumbnail(s)
   
Reply