Bhrahmani Inland Waterway
#1
Several news items on this on August 24th 2023:

See 

Following is an excerpt from the first one:

Quote:The Centre unveils an ambitious proposal for a Rs 120 billion inland waterway along the Brahmani river in Odisha. The objective is to facilitate the efficient movement of goods from four key industrial clusters to the ports of Paradip and Dhamra. The scheme envisions government-led infrastructure development using the engineering, procurement, and construction (EPC) model.

A collaborative special purpose vehicle (SPV) involving Coal India Limited (CIL), Inland Waterways Authority of India (IWAI), Paradip Port, and the Odisha government will spearhead the creation of the necessary infrastructure for operationalizing the National Waterway 5 (NW5). A senior government official affirmed that the concept has secured in-principle approval from the respective company boards.


See also 

Reply
#2
Following is from the 2016 act at https://www.indiacode.nic.in/bitstream/1...016-17.pdf

[Image: attachment.php?aid=495]

[Image: attachment.php?aid=494]
Reply
#3
Following is from https://www.iwai.nic.in/waterways/nation...-5?id=2527 , the official site.

[Image: attachment.php?aid=496]

[font="Open Sans", sans-serif][b]Salient features of National Waterway No. 5 - Brahmani river & Mahanadi delta system along with East Coast Canal (NW-5)[/b][/font]
[font="Open Sans", sans-serif]The Talcher- Dhamra stretch of river Brahmani, Geonkhali- Charbatia stretch of East Coast   Canal, Charbatia- Dhamra stretch of Matai river and Mangalgadi-Paradip stretch of Mahanadi delta rivers (NW-5, 623 km)[/font]
[font="Open Sans", sans-serif][b]Declared as National Waterway 5 (NW 5) on 25.11.2008[/b][/font]
[font="Open Sans", sans-serif][b]Detailed Project Report (DPR) prepared by M/s. WAPCOS[/b][/font]
[font="Open Sans", sans-serif][b]Length - 588 km. [/b]
River portion (371 km) 
Canal portion (217 km)[/font]

[font="Open Sans", sans-serif][b]Estimated Cost[/b] (at 2009 prices)
(i) Cost for development of River portion [b]Rs. 2230 cr[/b] (Barrages- 1843 cr)
(ii) Cost of development of canal portion [b]Rs. 1979 cr [/b](Dredging- 1273 cr) 
(iii) [b]Total Cost Rs. 4209 crore[/b][/font]

[font="Open Sans", sans-serif][b]Period of Completion[/b] - [b]7 years[/b]
[b]Land Acquisition: [/b]
in West Bengal - 846 Ha
in Orissa - 1172 Ha required 
Estimated cost of land acquisition - [b]Rs. 176 Crore[/b][/font]

[font="Open Sans", sans-serif][b]Details of dredging[/b]
River portion - 10.07 million cum
Canal portion - 44.77 million cum[/font]

[font="Open Sans", sans-serif][b]Barrages [/b]
To maintain LAD of 2 m in the Brahmani river all through the year, 5 barrages with height equal to the highest flood level are proposed to be constructed at every 26 km between Talcher and Jokadia. Each barrage will have a navigational lock to allow passage of two 500 tonne vessels at a time.[/font]

[font="Open Sans", sans-serif][b]Cargo potential[/b]
Coal from Talcher to Dhamra and Paradip ports is the most important potential cargo for this waterway. Immediately after the development of the waterway, it is estimated in the DPR that about [b]11 million tonne of cargo[/b] can be transported per year which can go up to 23 million tonne in next 15 years or so.[/font]

[font="Open Sans", sans-serif][b]EIRR[/b]
River portion 31.77%
Canal portion 12.75%
Rive and canal together 23.75%[/font]

[font="Open Sans", sans-serif][b]Phase – I activities are as follows :-[/b][/font]
  1. Detailed Hydrographic Survey (Phase-II) from Talcher to Pankapal : 120 Km length- completed in October, 2020.

  2. Monthly Thalweg Survey (Phase–I) from Pankapal to Dhamra - Paradip via. Mangalgadi : 230 LKM per month – Monthly Thalweg Survey conducted & LAD report issued monthly basis.

  3. Consultancy for preparation of DPR including FEED for construction of 4 Weirs cum Barrages with 3 Navigation locks, 2 Check Dams & 1 Rubber Dam with Nav. Lock (Phase-I) – The DPR is likely to be completed by March, 2021.

  4. Consultancy for preparation of DER including DEDD for Modification / Reconstruction of existing Bridges on NW-5 (Phase-I) – The DPR is likely to be completed by March, 2021.

  5. EIA / EMP study between Paradip / Dhamra and Pankapal (Fairway development) (Phase-I).

  6. Shifting / Relocation of HT / LT Power lines in NW-5 (Phase-I)- The work was entrusted to Govt. of Odisha (Deposit basis).
[font="Open Sans", sans-serif][b]For Executive Summary of DPR Click here[/b][/font]

[*][font="Open Sans", sans-serif][b]
Mathematical Model Study Report for Brahmani River System NW5  (PDF, 9818 KB)
[/b][/font]


[*][font="Open Sans", sans-serif][b]Final DPR of NW-5  (PDF, 20658 KB)[/b][/font]

[*][font="Open Sans", sans-serif][b]Project Development Consultancy for Development of National Waterway - 5 in PPP mode[/b][/font]


Attached Files Thumbnail(s)
   
Reply
#4
The 2022 EOI on NW-5 and NW-64. See https://odishadev.odishasociety.org/atta...hp?aid=497 and https://odishadev.odishasociety.org/atta...hp?aid=499 for the pdfs.

[Image: attachment.php?aid=498]


Attached Files Thumbnail(s)
   

.pdf   EoI_d.pdf (Size: 640.46 KB / Downloads: 3)
.pdf   NIT (2).pdf (Size: 167.52 KB / Downloads: 0)
Reply