KB Khurda-Balangir line: fast progressing - to be completed by 2027
#21
As per https://x.com/OdishaRail/status/1929178365501591798  and https://x.com/OdishaRail/status/1929178752581316676 


Quote:T2 tunnel has achieved breakthrough marking a special moment as now all seven tunnels are in various stages of construction of Khurda Balangir line.

T2 tunnel is 1775 metres long with a curve in it.
Reply
#22
Latest status of various segments and stations:
  1. Balangir (302)
  2. Bichhuapali (286.258) - operational (Weekly new18421 Puri-Sonepur express, Daily 12893/4 extended.)
  3. Jhartarbha (275.608)  - operational  (Weekly 18421 Puri-Sonepur expressDaily 12893/4 extended.)
  4. Narsinghgarh - NSGR (old name - Khambeswarpalli) (264.208) - operational (Weekly 18421 Puri-Sonepur expressDaily 12893/4 extended.)
  5. Sonepur (253.908) - operational (PM inaugurated on 2nd Feb 2024 and introduced Weekly 18421 Puri-Sonepur express, Daily 12893/4 extended.). 
  6. Purnapani (244.558) - operational (starting 20th June 2025 by PM's inauguration) https://www.youtube.com/watch?v=u5qq4LZO...uDaniVlogs , nov 25, 2023 https://www.youtube.com/watch?v=aGlnueXI...imodalNews, Signal testing on March 29, 2024 https://twitter.com/OdishaRail/status/17...6416747727 , CRS inspection on June 15th 2024 https://www.youtube.com/watch?v=IzjASa4w...=ARVEEVLOGhttps://www.youtube.com/watch?v=XQJGbLDA...TRAVELVLOG  
  7. Jharmunda (224.158) operational (starting 20th June 2025 by PM's inauguration) https://www.youtube.com/results?search_q...munda+railhttps://www.youtube.com/watch?v=5iIlRHm6...uDaniVlogs , Oct 11, 2023: https://twitter.com/EastCoastRail/status...p_TLQ&s=19 , Dec 16, 2023 https://www.youtube.com/watchv=VV5uvUHTb...=ARVEEVLOG , Matrch 30 2024 Engine Run: https://www.youtube.com/watch?v=9foIworQ...imodalNews , July 17 2024 CRS completed https://www.youtube.com/watch?v=Qfr0JITJ...=ARVEEVLOG 
  8. Boudh (207.888) operational (starting 20th June 2025 by PM's inauguration) https://www.youtube.com/results?search_query=Boudh+rail+ , https://www.youtube.com/watch?v=nEf9Ui1h...imodalNewshttps://www.youtube.com/watch?v=p_HPo8ak...uDaniVlogshttps://www.youtube.com/watch?v=zhMehUQ8...=ARVEEVLOG , May 3 2024 https://www.youtube.com/watch?v=WdcQCIa_...nPutelVlog , Jun 14th 2024: https://www.youtube.com/watch?v=pNcYU9ne...njuVlogger , June 17th 2024 https://www.youtube.com/watch?v=Dt5sGtQl...=ARVEEVLOG , June 30th 2024 https://www.youtube.com/watch?v=MYBm6tNy...=ARVEEVLOG, Aug 17, 2024: CRS completed https://pragativadi.com/another-mileston...missioned/ 
  9. Champapur (194.187) operational (starting 20th June 2025 by PM's inauguration) https://www.youtube.com/results?search_q...r+Balangir , March 31 2024 rails placed near station that is being built: https://www.youtube.com/watch?v=iqWTn4fV...=ARVEEVLOG , July 10, 2024 https://www.youtube.com/watch?v=vlGcO0Sv...=ARVEEVLOG ; Engine rolling done September 28th 2024 See https://x.com/OdishaRail/status/1840395600484823372 
  10. Puranakatak (180.75) - operational (starting 20th June 2025 by PM's inauguration) https://www.youtube.com/results?search_q...ay+stationhttps://www.youtube.com/watch?v=8mkXO4Xc...BzdGF0aW9uhttps://www.youtube.com/watch?v=nEf9Ui1h...imodalNewshttps://www.youtube.com/watch?v=TQ_kbFj_...uDaniVlogs , October 9, 2023: https://twitter.com/EastCoastRail/status...G823w&s=19 ; Feb 28, 2024: https://www.youtube.com/watch?v=ew0EEQdj...imodalNews ; April 18, 2024: https://www.youtube.com/watch?v=8yN-QcdH...=Dilsebiju , June 15 2024: https://www.youtube.com/watch?v=0DqK0MN2...=Dilsebiju , July 9 2024 https://www.youtube.com/watch?v=Qf1Lc9mI...=ARVEEVLOG Engine rolling done on September 29th 2024 https://www.youtube.com/watch?v=yUxN6mw1...mahibevlog 
    Towards Charichak: July 20 2024: https://www.youtube.com/watch?v=cb8-Y0cp...=ARVEEVLOG 
    Tunnel T7: With a length of 1975 meters, Tunnel T7 extends from Km 168+528.1 to Km 170+501.7. (Tunneling completed on August 20, 2024 https://kalingatv.com/odisha/ecor-reache...e-project/ )
  11. Charichak (167.4) - Forrest clearance received in Feb 2023 ; https://www.youtube.com/watch?v=dGrmPtfs...=ARVEEVLOG  (Expected to be completed by 2026-27)
    Station work: May 22, 2025 https://www.youtube.com/watch?v=VjER5paG...mahibevlog Tunnel T6: With a length of 315 meters, Tunnel T6 extends from Km 165+000.6 to Km 165+279.8.Tunnel T5: Tunnel T5 covers a distance from Km 164+464 to Km 164+780.68, spanning 317 meters: done https://pragativadi.com/khurda-road-bala...e-by-2026/ Tunnel T4: This engineering marvel stretches from Km 156+231.5 to Km 160.415, boasting an extraordinary length of 4185 meters, there’s also a 700-meter escape tunnel ensuring safety.  

    Two viaducts (1.3 kms and 0.55 kms): From https://sambadenglish.com/latest-news/od...ce-8647814 : May 2025 status of Charichak Harbhanga road viaduct near Karanjkata village  https://www.youtube.com/watch?v=Jj1gkQrcOko ; June 17 2025 status: https://www.youtube.com/watch?v=vk-NxyOMDTA 

  12. Adenigarh (153.75) - Forrest clearance received in Feb 2023 ; https://www.youtube.com/watch?v=65dng_qo...=ARVEEVLOG  ; March 29 2024 Tunnel construction initiated https://www.youtube.com/watch?v=hooyRrHj...=ARVEEVLOG (Expected to be completed by 2026-27)

  13. Baniguchha (139.75) - Forrest clearance received in Feb 2023 (Expected to be completed by 2026-27)

    Tunnel T3 (2,620 mtr length, ch 126.420 km to ch 129.040

    Two viaducts (#302 of 4.8kms and 0.29 kms): From https://sambadenglish.com/latest-news/od...ce-8647814 . The 4.8 km one will be the second longest rail viaduct in India and as per https://www.constructionworld.in/transpo...026-/75174 is expected to be complete by August 2026. 

  14. Buguda (121.8) - Forrest clearance received in Feb 2023 : September 15 2023 - https://www.youtube.com/watch?v=XW8we3se...imodalNews  , March 31 2024  ground work https://www.youtube.com/watch?v=6j1OB_rR...=ARVEEVLOG (Expected to be completed by 2026-27)
    Tunnel T2 (1775 M Length, Km 108.225 To Km 110.000): Tunnel breakthrough on June 1 2025; all tunnels have breakthrough now : https://x.com/OdishaRail/status/1929178365501591798 
    Tunnel T1 (800 M Length, Km 106.825 To Km 107.625): 

  15. Dasapalla (105.875) - operational (From Jan 2024) (https://erail.in/train-enquiry/18424https://erail.in/train-enquiry/08556 )
  16. Nuagaon Road (90.43) - operational (https://erail.in/train-enquiry/08423 and https://erail.in/train-enquiry/08429 )
  17. Mahipur (77.38) - operationa(https://erail.in/train-enquiry/08423 and https://erail.in/train-enquiry/08429 )
  18. Nayagarh town (65.456) - operational (https://erail.in/train-enquiry/08423 ,  https://erail.in/train-enquiry/08429https://erail.in/train-enquiry/08555https://erail.in/train-enquiry/18423 )
  19. Bolgarh Road (54.32) - operational (https://erail.in/train-enquiry/08423https://erail.in/train-enquiry/08429https://erail.in/train-enquiry/08555 , https://erail.in/train-enquiry/18423)
  20. Rajsunakhala (41.5) - operational (https://erail.in/train-enquiry/08423 ,  https://erail.in/train-enquiry/08429https://erail.in/train-enquiry/08555 , https://erail.in/train-enquiry/18423)
  21. Begunia (32) - operational (https://erail.in/train-enquiry/08423https://erail.in/train-enquiry/08429https://erail.in/train-enquiry/08555https://erail.in/train-enquiry/18423 )
  22. Khurda Town (13.35) - operational (https://erail.in/train-enquiry/08423https://erail.in/train-enquiry/08429https://erail.in/train-enquiry/08555https://erail.in/train-enquiry/18423 )
  23. Khurda Rd (0)
Reply
#23
[Image: attachment.php?aid=989]


Attached Files Thumbnail(s)
   
Reply
#24
Earlier the line was operational upto Soneput. The PM inaugurated the 73km extension from Sonepur to Purnakatak on 20th June 2025.

Following is from https://x.com/OdishaRail/status/19359360...60/photo/1

[Image: attachment.php?aid=990]


Attached Files Thumbnail(s)
   
Reply
#25
From https://forum.irfca.org/threads/train-in...ost-781977 

Quote:1.Introduction of Train No 18313/14 Boudh - Bhubaneswar New weekly Express & Train No 18311/12 Boudh Sambalpur weekly express wef 23/6/2025.

2. Extension of three train services to #Purunakatak from June 23rd.

(1) Train No. 12893/12894 (BBS-SNPU-BBS) Daily Intercity Express: Extension to
PURUNAKATAK (PUKK)

2)Train No. 58305/58306 (Balangir-Sonepur-Balangir) daily Passenger: Extension up to 'PURUNAKATAK' (PUKK) with revised Timings

(3)Train No. 58307/08308 (Balangir-Sonepur-Balangir) Passenger: Extension up to PURUNAKATAK (PUKK) with revised Timings
Date of Extension up to Purunakatak: Train No. 58307 JCO w.e.f. 23.06.2025 Ex- Balangir

[Image: attachment.php?aid=991]

[Image: attachment.php?aid=992]

[Image: attachment.php?aid=993]

[Image: attachment.php?aid=994]


Attached Files Thumbnail(s)
               
Reply
#26
So as of today (20th June 2025) the summary of this line is:

Balangir (302)
... operational with trains
Puranakatak (180.75)
-- Tunnel T7: With a length of 1975 meters,
extends from Km 168+528.1m to Km 170+501.7m.
Charichak (167.4)
-- Tunnel T6: With a length of 315 meters, extends from Km 165+000.6 to Km 165+279.8.
   Tunnel T5: from Km 164+464m to Km 164+780.68m, spanning 317 meters:
   Tunnel T4: from Km 156+231.5m to Km 160.415m, length of 4185 meters,
   there’s also a 700-meter escape tunnel ensuring safety.
-- Two viaducts (1.3 kms and 0.55 kms):
Adenigarh (153.75)
Baniguchha (139.75)
-- Tunnel T3 (2,620 mtr length, ch 126.420 km to ch 129.040
-- Two viaducts (#302 of 4.8kms and 0.29 kms)
Buguda (121.8)
-- Tunnel T2 (1775 M Length, Km 108.225 To Km 110.000):
   Tunnel T1 (800 M Length, Km 106.825 To Km 107.625):
Dasapalla (105.875)
... operational with trains
Khurda Road (0)

All tunnels have been broken through.


My guess is that within a year (by 2026) lines up to Buguda from Khurda Rd side and up to Charichak from Balangir side will be done. The whole line will be completed in 2027 after the completion of the 4 viaducts.
Reply